Bullet Train Update: Big update is revealed regarding Indias First Bullet Train. Railway Minister Ashwini Vaishnav stated on Friday that the country’s inaugural high-speed rail service will commence in the final quarter of 2027, initially running between Surat and Vapi.
Bullet Train Update
In a post on ‘Substack’, he added that the rail service will be gradually extended along the entire corridor up to Mumbai. Regarding the construction progress, he reported that by September, pillars have been erected for 456 km and viaducts (elevated railway bridges) constructed over 371 km.
He noted that civil construction at eight stations has been completed, with final architectural work currently underway. Vaishnav also mentioned ongoing work on three depots for train maintenance located in Sabarmati, Surat, and Thane. He further highlighted that the construction of India’s first bullet train is in progress.
“Integrated Coach Factory (ICF) and BEML are manufacturing the indigenous B28 trainset, designed to operate at speeds up to 280 km/h. The first frame has been completed and is undergoing structural testing, with track testing anticipated by mid-2027. The B35 trainset, capable of speeds up to 350 km/h, will follow,” Vaishnav said.
Meanwhile The Mumbai-Ahmedabad bullet train project reached a significant milestone on Friday. The overhead power line for the 50-kilometer section between Surat and Bilimora in Gujarat was commissioned on November 20th. This marks the first time electricity has been supplied to a section of the country’s first high-speed rail corridor. This will accelerate preparations for the bullet train service on this route.
The country’s first bullet train service will commence in the last quarter of 2027 and the first section to open will be from Surat to Vapi.
– Minister Ashwini Vaishnaw. https://t.co/RFTsVp1rSl
“>November 21, 2026
Power Supply Starting on 50 km of Track
A modern 2×25 kV overhead traction system has been installed on both the up and down lines of this section. Once power is restored, the wires will remain live at all times. The National High Speed Rail Corporation Limited (NHSRCL) has warned nearby residents, passengers, and construction workers to stay away from the wires and avoid touching or working near electrical equipment without permission.